REPUBLIC OF CAMEROON Peace - Work - Fatherland
REPUBLIC OF CAMEROON Peace - Work - Fatherland
MINISTERE DE LA DECENTRALISATION ET DU DEVELOPEMENT LOCAL ***
MINISTERE OF DECENTRALIZATION AND LOCAL DEVELOPMENT ***
DELEGATION REGIONALE DU NORD OUEST ***
NORTH WEST REGIONAL DELEGATION ***
DEPARTEMENT DE NGOKETUNJIA ***
NGOKETUNJIA DIVISION ***
ARRONDISSEMENT DE BALIKUMBAT ***
BALIKUMBAT SUB DIVISION ***
COMMUNE DE BALIKUMBAT ***
BALIKUMBAT COUNCIL
# TENDER NOTICE
OPEN NATIONAL INVITATION TO TENDER FILE N° 06/ONIT/MINDDEVEL/NWR/NGOK./BC/BCITB/2026 OF 10/01/2026 FOR THE EXTENSION OF ELECTRICITY FROM GATEWAY TO BACKYIT QUARTER AND THE REHABILITATION OF ELECTRICITY LINE IN BALIGASHU AND BALIGANSIN VILLAGES ALL IN BALIKUMBAT MUNICIPALITY, NGOKETUNJIA DIVISION OF THE NORTH-WEST REGION.
Financing: PIB MINEE - 2026
- Subject of the Invitation to Tender:
Within the framework of 2026 Public Investment Budget, The Mayor of Balikumbat Council, Contracting Authority hereby launches an Open National Invitation to Tender for The Extension of Electricity from Gateway to Backyit Quarter and The Rehabilitation of Electricity Line in Baligashu and Baligansin Villages All in Balikumbat Municipality, Ngoketunjia Division of the North-West Region.
- Nature of work:
Work to be done consists of Construction works
☑ Construction of a MV Single phase line on a distance of 600m with 1x34.4 mm² Almelec Cables.
☑ Construction of a MV/LV Single phase line on a distance of 2,700m with 1x34.4 mm² Almelec Cable and 4x25mm² Aluminum Twisted Cable.
☑ Construction of a LV Single phase line on a distance of 1,500m with 4x25mm² Aluminum twisted cable.
☑ Construction A Transformation Substation Equipped with Two Single-Phase Transformers H61-25 KVA/17.32KV;
☑ Rehabilitation of a MV Single Phase Line on a distance of 350m with 1x34.4 mm² Almelec Cable;
☑ Rehabilitation of MV/LV Single Phase Line on a distance of 800m with 1x34.4mm² Almelec & 4x25 mm² Aluminum Twisted Cables;
☑ Rehabilitation of LV Single-Phase Line on a distance of 1,700m with 4x25 mm² Aluminum Twisted Cable;
☑ Replacement of Transformer Poles in Some Transformation Station H61-25KVA/17.32KV;
☑ The Sundry expenses will consist of:
☑ Clearing and pruning 8m width on each side of the network.
☑ Transportation of wooden and galvanized poles, materials and workers.
- Execution deadline
The maximum deadline provided by the Delegated Contracting Authority for the execution of the works forming the subject of this Invitation to Tender is three (03) months
4. Lot
The work is in single lot as follows: Extension of Electricity from Gateway to Backyit Quarter and The Rehabilitation of Electricity Line in Baligashu and Baligansin Villages All in Balikumbat Municipality, Ngoketunjia Division of the North-West Region.
5. Estimated cost
The estimated cost after preliminary studies is 100,000,000 FCFA (One Hundred million FCFA)
6. Participation and origin
Participation to this Invitation to Tender is opened to Cameroonian enterprises that are in compliance with the Cameroon laws.
NB: Bidders should not complain of insecurity at the site during the execution of the project.