RésuméLe Premier Ministre camerounais Joseph Dion Ngute a présidé une réunion du Cabinet le 29 juillet 2020, consacrée à l'examen des projets autoroutiers. Le Ministre des Travaux Publics a présenté l'avancement des autoroutes Yaoundé-Douala et Edéa-Kribi-Lolabe, avec des taux d'exécution de 91% et 88,14% respectivement. Le Ministre de l'Habitat et du Développement Urbain a fait le point sur l'autoroute Yaoundé-Nsimalen (90% d'avancement). Le Ministre de la Santé Publique a présenté l'évolution de…

PRIME MINISTER'S OFFICE SECRETARIAT GENERAL REPUBLIC OF CAMEROON Peace-Work-Fatherland

# PRÈSS RELEASE FOLLOWING CABINET MEETING OF WEDNESDAY 29 JULY 2020


The Prime Minister, Head of Government, His Excellency Joseph DION NGUTE, today Wednesday 29 July 2020 at 10 a.m. through video conference, chaired a Cabinet Meeting devoted to the review of motorway projects, attended by Ministers of State, Ministers, Ministers-Delegate and Secretaries of State.

During this Meeting, the Minister of Public Works and the Minister of Housing and Urban Development respectively presented the current situation, challenges and outlook of the Yaounde-Douala and Kribi-Edea motorway construction projects, and the Yaounde-Nsimalen motorway.

The Minister of Public Health also presented the weekly update on the evolution of the COVID-19 pandemic in Cameroon.

Taking the floor following the Prime Minister’s introductory statement, the Minister of Public Works indicated that the motorway programme initiated by the President of the Republic provides for the medium and long term construction of the Yaounde-Douala motorways (196 km), Edéa-Kribi-Lolabe (130 km), Bafoussam-Bamenda (116 km), the Yaoundé/Douala-Bafoussam intersection (250 km) and Yaoundé-Ngaoundéré-Garoua-Maroua-Kousseri-Ndjamena (about 1500 km). The first phase of this vast programme was launched in 2014, with the start of construction work on the Yaoundé-Douala and Edéa-Kribi-Lolabe motorways.

With regard to the Yaoundé-Douala motorway, work on the 60-km long Yaoundé-Bibodi section has been completed by over 40 km, with 20 km of recovery lanes. Signalling and slope protection remain to be completed. The physical execution rate is 91% and the completion date for this section is set for 31 December 2020. In addition, several social collective facilities such as boreholes and classrooms have been built, as part of the environmental and social management plan of the project.

For the second section, Bibodi-Douala which is 136 km long, the summary studies were validated on 14 November 2019 and the Public-Private Partnership procedure was launched. The signature of the related contract is envisaged for 30 March 2021, with a view to starting the works. The main challenges relate to the release of rights of way, the payment of compensation and the mobilization of additional funding.

With regard to the Edéa-Kribi-Lolabe motorway, the Minister of Public Works said that this project is part of the improvement of the competitiveness and attractiveness of the Kribi Port Authority. The works on the Kribi-Lolabe section, 38.5 km long, are 88.14% completed. Two major challenges are hindering the execution of the works, namely the payment of residual compensation and settlement for the works already executed.

Negotiations are underway to structure a public-private partnership contract with the project’s technical and financial partners.

For the Edéa-Kribi section, 92 km long, the notice of expression of interest was launched on 4 March 2020 for the selection of companies responsible for carrying out the work. The bids submitted on 30 June 2020 will be examined by the dedicated Special Commission which is currently being set up.

Texte intégral

Lisez l'intégralité de ce texte

Créez un compte gratuit pour accéder au texte complet, au PDF officiel et à la recherche juridique assistée par IA.

Lire l'intégralité — inscription gratuite
Inscription gratuite Accès immédiat PDF officiel inclus

Déjà un compte ? Se connecter

Parcourir les texte juridiques